2. EXCAVATION AND EARTHWORK
- Exiting
ground level indicated as +/- in drawings shall be the level of trimmed
ground free of all structures, pavings, plinths, foundations, and
the like.
- The
Contractor is advised to inspect the Soil Investigation Report which
is available with the Employer in order to determine the type of soil
generally encountered.
- The
Contractor is required to inspect the site in order to acquaint himself
with the condition of site and the subsoil, prior to preparing his
tender.
- Surplus
excavated materials not suitable for filling shall be removed at the
expense of the Contractor.
- The
Contractor must obtain all detailed information from the relevant
authorities in compliance with relevant acts, by-laws, and regulations,
on excavations, planking, and strutting.
- The
Contractor shall submit samples and obtain test certificates as required
by the contract documents.
- The
rate for compacted earth fill and granular fill, stone, gravel, and
sand beds, shall include for imported materials or materials from
borrow areas. If any excavated materials arising from construction
works are used an adjustment will be made in the Final Account on
the rates of applicable materials.
- Planking
and strutting measured shall include additional width of excavation
as required by the Standard Method of Measurement if measured separately.
- Rates
for Excavation and Earthwork shall include for-
-
Excavating by whatever means are necessary including excavation
by manually or by machinery, in any type of ground including boulderised
ground but except in rock.
- Trimming
sides, keeping clean and consolidating bottom of bases and trenches
unless measured separately.
- ack
filling and disposal of surplus excavated materials as specified
and directed.
- Any
necessary additional excavation for working space, planking and
strutting, form work etc.
- Rates
for all excavation works shall include for dewatering works, using
pumps, if the need arises due to ground water condition or rain.
Planking and Strutting
Note
:
- Payment
for planking and strutting will only be considered on actual quantities
of work executed.
- Planking
and strutting shall be carried out only if specifically instructed
to do so by the Employer.
v.
Any additional trimming or appropriate back filling to provide the
specified or approved formation and profile, necessitated by the
uneven excavation of earth, unless measured separately
- Rate
for compacted earth fill and granular fill and gravel and sand beds
shall include for grading to slopes and falls, depositing in layers,
levelling, blinding, machine or hand packing to form vertical or battered
or level faces, and for forming sinking required under floor slabs
or sub-floor layers.
- Rate
for Damp Proof Membrane or polythene sheeting are to include for laps
and straight, raking and circular cutting, and for notching around
all obstructions.