6. PAINTING
- Rate
for painting shall include for-
- Preparation
of surfaces, cleaning, and smoothening, by sand paper or glass
etc.Where smoothening or evenness cannot be obtained due to uneven
plastering, the contractor shall apply masonry filler repeatedly
at his cost to obtain an even surface.
- Protection
of floor, walls, and fittings, etc.
-
Working at any height, working to returns, pointing in any colour,
multi-colour work if any, and painting in small quantities.
-
Cleaning on completion.
- The
rates for work to isolated general surfaces shall include for working
on door frames, linings, window subframes (if different from window),
skirting, rails, architraves, bars, posts, balusters, and the like.
-
Rates
for glazed general surfaces, glazed windows and the like (measured
flat over glass irrespective of size of pane), shall include for
work to edges and glazing rebates, returns and mouldings of frames,
mullions, transoms, architraves, and the like.
- The
rates to work to pipes and conduit, (including trunking, ducting,
and the like), shall include for all work on hangers, supports, brackets,
and the like.