14(1)

Where a plan of any development activity is submitted under the Law, Authority may approve the plan with or without any terms or conditions imposed within 8 weeks from the registered date of application and, in the case of a temporary building, a plan or the application for permission to erect the building may be approved by the issue of a temporary permit on such terms and conditions as the Authority thinks fit.

(2)

A temporary permit for the erection of a temporary building which is issued under paragraph (1), shall be valid for such period of time as may be specified in that permit.

3)

Where the temporary building is -

(a) a shed for entertainment purposes; or

(b) a shed for funeral, religious or other purposes; or

(c) a builder's working shed or store or any other shed used in connection with any new building works; or

(d) a hoarding or frame for the display of advertisements or sign boards or other advertising devices; or

(e) a protective hoarding, catch platform or sidewalk shed on street orfootway in connection with any building works; or

(f) a scaffolding on a street ; or

(g) a stall or shed in a building or other premises for trade fair fun fair or exhibition purposes,the permit shall be valid for not more than one year.

(4)

On the approval of a plan of any building or building works the Authority shall notify the owner of the building or the premises in which the building works, are to be commenced, carried out or resumed and any qualified person who prepared the plan or who is to supervise the building works of such approval and of the terms or conditions, if any, on which such approval has been granted and shall return one copy of the plan to the applicant/owner.

(5)

Where there is a contravention or mispresentation of facts or a failure to comply with a term or condition on which an approval or a permit is granted under this regulation, such approval or permit, as the case may be, shall be revoked.


Disapproval of the plans
15.

Where the Authority disapproves a plan of any development activity submitted under the Law, the Authority shall notify the owner of the premises n which the development ativities are to be commenced, carried out or resumed and any qualified person who prepared or submitted the plan under regulation 3 or who is to supervise the building works under paragraph (c) of regulation 16 of such disapproval with the reasons therefore and return one copy of the plan to the owner or qualified person within 4 weeks from the registered date of the application and retain the fees.