| Certificate
of conformity for occupation |
| 22.
| The Authority may
grant a certificate of conformity for the occupation of a building or part thereof
or any other development activities when
|
| (a) |
every certificate and report
in respect of the building or part thereof or any other development activity have
been submitted to the Authority pursuant to the provisions of regulation 13;
|
| (b) |
all the requirements shown
on the plan or plans and all the written directions given by the Authority to
the qualified person or persons,who prepared the plan or the building or part
thereof or the building works under paragraph
|
| (c) |
of regulation 16, have
been complied with and a certificates from the qualified person is forwarded to
that effect; and (c) all the fees payable under these Regulations have been paid.
|
Inspections
by the authority |
| 23. | (1)
|
The Chairman or his authorised representative may enter upon and inspect at all
reasonable times a building before a certificate of conformity for the occupation
thereof is issued under regulation 22 or any building works at any stage thereof
for the purpose of determining whether all the provisions of the Law and these
Regulations have been complied with, and of calling the attention of the qualified
person or persons who prepared the approved plan or plans of the development activity
to any deviation from the approved plan or any other plan of the development activity
submitted under these Regulations or to any non-completion of the development
activity in accordance with such plan or plans or to any non-compliance with a
provision of the these Regulations or the plan or plans or a requirement shown
thereon which he may have to observe.
|
| (2)
| The
authorised representative of the Authority shall, before entering upon and inspecting
a building or any development activity under paragraph (1) identify himself by
producing and exhibiting his written authority |
Licence
for the temporary occupation of the building |
| 24 | (1) |
Notwithstanding the fact
that a certificate of conformity for the occupation of a building or part thereof
is not issued because of a deviation from the approved plan or plans of compliancthe
building or non-compliance with a requirement endorsed on the plan or plans by
the Authority or non-completion of the building works in respect of the building,
the Authority may grant or renew a licence for the temporary occupation of such
building or part thereof for a period not exceeding six months at a time if the
deviation, non-compliance or non-completion is in his opinion neither of a serous
nature nor in any way detrimental to the well-being and safety of the person or
persons who may occupy the building or part thereof during such period.
(2)
A licence may be granted or renewed under paragraph (1) on such terms or conditions
as the Authority thinks fit and shall be revoked on a breach of any of those terms
or conditions.
|